Another rainy night in Rotherham, another 180 buckets overflowing with rainwater in the steadily decaying 18th century rooms at Wentworth Woodhouse.

When the Preservation Trust took over the Grade I listed stately home in March 2017 with just six staff, emptying the buckets and mopping up was one of many backbreaking and crucial tasks.

But the buckets are now redundant, and the Trust is celebrating a major milestone.

After almost two years of specialist repairs to the roof over the State Rooms, costing £5.5million, Phase 2 of the repair programme is now complete and the majority of the Palladian-style East Front of the mansion is now water-tight.

Ancient, overflowing guttering and drainpipes have been repaired or replaced, stone features created by artisan masons almost 250 years ago have been painstakingly restored.

Emergency roof repairs have also made endangered sections of the historic Stables and Riding School safe.

The achievements and challenges of this colossal project, which was carried out on-budget, and remained on-schedule during the pandemic, were highlighted at a celebratory event on Wednesday October 6.

Gathered in the mansion’s Long Gallery, where rows of rain buckets stood before its own roof repairs were carried out, trustees, supporters and representatives from the organisations who had played their part heard how many years of neglect have been repaired to the highest of conservation standards and the workload involved.

Phase 2 repairs began in 2019. Urgent works across the site had been carried out from August 2017 to March 2019, and Phase 1 repairs at the Riding School and the mansion’s Bedlam Wing and Chapel ran from March 2018 to January 2020.

The three repair projects were funded by a £7.6 million Treasury grant awarded to the Trust by chancellor Philip Hammond in his Autumn 2016 Statement.

Before Phase 2 work could start, scaffold on an epic scale had to be designed. Once erected it encased the mansion in a shell comprised of 700 tonnes of scaffold poles towering 30 metres tall.

Pic credit: Carl Whitham

Then heritage craftsmen working for project contractors Robert Woodhead Ltd, with guidance and support from Historic England and architects Donald Insall Associates, began repairing roofs the size of three football pitches over the mansion’s central block and Long Gallery.

The Trust’s CEO Sarah McLeod said: “The project has been one of the most exciting and challenging heritage projects of a generation. Every single person involved has played a vital role - from the contractors through to our volunteers who led tours on our rooftops, enabling the public to watch work progressing.

She added: “We’ve had many challenges to go through. The scale of Wentworth Woodhouse and its sad state brought particular problems, which expertise and skill overcame.

“Then came the global pandemic. We overcame that too – the site was closed for just five weeks and supplies of materials were maintained.

“The project has been a triumph. The building is now protected for future generations to enjoy and the Preservation Trust can move on to other vital repair and restoration tasks.”

In January 2021, specialist conservators were also able to start essential repairs to the roof of the North Pavilion, which sits at one end of the Palladian East Front, and the North and South Quadrants.

 